The Coolstore level crossing removal project is a SEPA project that removed a level crossing (rail over road), redeveloped the road network around the station and level crossing, and installed new road crossings under the rail. 

Services Provided

  • FSC assisted with the development and implementation of short and medium programs for the construction of crane and piling pads
  • Worked with geotechnical engineers to rectify unsuitable subgrade material
  • Liaised with stakeholders to ensure that construction methodology around assets was suitable
  • Developed the construction methodologies for working platforms

Client

Laing O’Rourke

Location

Croydon, Victoria

Value

$572m

Year

2023 - 2024

Image of person

The Coolstore level crossing removal project is a SEPA project that removed a level crossing (rail over road), redeveloped the road network around the station and level crossing, and installed new road crossings under the rail. 

Services Provided

  • FSC assisted with the development and implementation of short and medium programs for the construction of crane and piling pads
  • Worked with geotechnical engineers to rectify unsuitable subgrade material
  • Liaised with stakeholders to ensure that construction methodology around assets was suitable
  • Developed the construction methodologies for working platforms

Related

View All
Image of harbor

SUP Widening Superintendent

  • Engineering Management
  • Planning & Project Controls
  • Project Management
  • Community Infrastructure
Image of chart

SRL Utilities Design Management

  • Engineering Management
  • Planning & Project Controls
  • Project Management
  • Structures & Maritime Design
Image of person

Access Ramps Superintendent

  • Engineering Management
  • Planning & Project Controls
  • Project Management
  • Community Infrastructure