Cranbrook Rail Outloading Project

The project involved extending the existing rail siding by 1 km to reduce congestion at level crossings and constructing a new 6,600-tonne fixed rail loading facility to enhance efficiency. Previously, loading a 60-wagon train took seven hours, but upon completion, it is expected to take only four hours.

Services Provided

  • Assisted with design management.
  • Managed civil quality documentation.
  • Compiled end-of-month claim substantiation documents.
  • Conducted daily monitoring of works.
  • Tracked crew and plant productivity.

Client

Laing O'Rourke

Location

Cranbrook, Western Australia

Value

$30m

Year

2024

Image of person

The project involved extending the existing rail siding by 1 km to reduce congestion at level crossings and constructing a new 6,600-tonne fixed rail loading facility to enhance efficiency. Previously, loading a 60-wagon train took seven hours, but upon completion, it is expected to take only four hours.

Services Provided

  • Assisted with design management.
  • Managed civil quality documentation.
  • Compiled end-of-month claim substantiation documents.
  • Conducted daily monitoring of works.
  • Tracked crew and plant productivity.

Related

View All
Image of harbor

SUP Widening Superintendent

  • Engineering Management
  • Planning & Project Controls
  • Project Management
  • Community Infrastructure
Image of chart

SRL Utilities Design Management

  • Engineering Management
  • Planning & Project Controls
  • Project Management
  • Structures & Maritime Design
Image of person

Access Ramps Superintendent

  • Engineering Management
  • Planning & Project Controls
  • Project Management
  • Community Infrastructure